Henriksdal WWTP-即將建成為世界上最大的地下MBR污水廠
Henriksdal wastewater treatment plant (WWTP) is located on the boundary between Stockholm and Nacka, approximately 2km from Slussen, Sweden. It currently serves approximately one million people in Stockholm and Huddinge, including Haninge, Nacka and Tyresö municipalities.
Operated by Stockholm Vatten (the Stockholm Water Company), the facility is one of the world's biggest underground WWTP and covers a total area of 300,000m³ with 18km of associated tunnels and a wastewater treatment capacity of roughly 250,000m³ a day. The sludge produced from the plant is treated at the neighbouring facility in Sickla.
Stockholm Vatten has proposed a major expansion and renovation for the WWTP in order to meet the city's growing population and enable the city to close down the Bromma WWTP, which is causing an obstruction to create more homes in western Stockholm. The project will enable the city to meet the effluent requirements set under the Baltic Sea Action Plan (BSAP) and EU water directive.
Integrating GE's proprietary LEAPmbr technology, the WWTP will be the world's biggest facility implementing the membrane bioreactor (MBR) technology when the project is realised in 2018. Construction works on the SKr5.94bn ($689.5m) are scheduled to start in 2016.
Henriksdal WWTP history and former expansions
Henriksdal WWTP was opened in 1941 with an initial treatment capacity of 150,000m³ a day, which increased to 300,000m³ a day in 1953. Chemical and biological treatment facilities were later incorporated into the plant's system.
"The WWTP will be the world's biggest facility implementing the membrane bioreactor (MBR) technology when the project is realised in 2018."
Executed from April 1992 to April 1997, a major expansion enabled the plant to reduce nitrogen emissions by approximately 50% and improve phosphorus treatment.
Another major reconstruction project was carried out from 2007 to 2011, which involved the construction of a new hall for rough purification and new receiving station for grease and organic waste. The project involved the blasting and excavation of 80,000m³ of rock, enabling the odour producing facilities to be reconstructed and placed underground. It facilitated the development of 3,000 new homes around Henriksdalsberget.
Facilities at Henriksdal WWTP
The plant treats wastewater using mechanical, chemical, biological and sand filtration processes following which the treated water is emptied into the Baltic Sea. The biogas produced from the plant is used as fuel in the plant's heat production system for the production of electricity and for producing biomethane for fuelling vehicles, while the produced sludge is used as a soil conditioner.
The WWTP is currently equipped with eight mechanical screens, two grit chambers with a volume of 590m³ each, two pre-aeration channels with a capacity of 260m³ each, 13 primary sedimentation tanks with a combined volume of 30,000m³, nine pumping stations to lift the primary-sedimentation to the biological stage, seven aeration tanks with a combined volume of 204,000m³ and 19,000 aerators, five aerator compressors, and 14 secondary sedimentation tanks with a combined volume of 58,000m³.
Furthermore, the plant is equipped with 12 pumps to lift the water from the biological stage to 60 sand filters, seven digesters with a combined volume of 39,000m³, a heat exchanger digester sludge, a 5,000m³ gas holder, five excess sludge centrifuges with a capacity of 50m³ a hour, two sludge tanks with a combined volume of 10,000m³, four centrifuges with a capacity of 30m³/h each for dewatering of sludge, two silos of 800m³ each for containing dewater sludge, four gas engines, three boilers and associated facilities.
Approximately 90% of the facilities at the site are located underground. The surface facilities include control centre building, mechanical treatment facilities, sludge tanks and upper parts of the sludge thickeners, digesters, gas holder, and gas collection and gas storage facilities. The plant's old ventilation chimney measuring 80m-high and 7m in diameter is currently being reinforced with concrete.
Details of the Henriksdal WWTP expansion and renovation project
A pilot project to test the MBR technology, taking into account a load equal to Stockholm's projected population in 2040, was concluded in 2014. GE's LEAPmbr technology which integrates its ZeeWeed 500 membrane is an advanced ultrafiltration technology that separates solids, bacteria and viruses from water or wastewater.
The pilot test was performed at IVL's (Swedish Environmental Research Institute) Hammarby Sjöstadsverk research facility. The positive results from the test gave further impetus to the current project. The expansion and renovation will enable the WWTP to treat 864 million litres of wastewater a day.
In addition to installing the new membrane distillation units at the Henriksdal site, the project will involve the construction of a 15km underground tunnel, bored from 30m to 90m below ground level, to divert the wastewater from Bromma to Henriksdal. A new pre-treatment facility comprised a new pump station, new coarse screening and primary sedimentation basins will also be built at Sickla.
The decommissioning of the Bromma WWTP will start following the commissioning of the revamped Henriksdal WWTP.
Contractors involved with the Swedish WWTP
The planning and design works for the reconstruction of the WWTP were performed from 2007 to 2011 by Sweco. In 2010, Mercor installed fire doors and gates at the site.
The contract to deliver the electrical solutions including telecommunications and automation solutions for the current project has been awarded to ÅF Group.
文章轉(zhuǎn)載http://www.water-technology.net/
Henriksdal污水廠——即將建成為世界上最大的地下MBR污水廠
2015-05-12水進(jìn)展
Henriksdal污水處理廠(污水廠)位于斯德哥爾摩和Nacka之間的邊界,從Slussen約2公里,瑞典。目前大約有一百萬人在斯德哥爾摩和Huddinge,包括Haninge Nacka Tyreso直轄市。
由斯德哥爾摩Vatten(斯德哥爾摩水務(wù)公司),該設(shè)施是世界上最大的地下污水廠之一,占地總面積300000 m³18公里的隧道和廢水處理相關(guān)的能力約250000 m³一天。從植物處理產(chǎn)生的污泥在Sickla鄰近設(shè)施。
斯德哥爾摩Vatten提出了一個(gè)主要的擴(kuò)張和污水廠的改造,以滿足不斷增長的城市人口,使城市關(guān)閉Bromma污水廠,這是造成阻塞在斯德哥爾摩西部創(chuàng)造更多的房屋。該項(xiàng)目將使城市達(dá)到廢水要求設(shè)置在波羅的海的行動(dòng)計(jì)劃(BSAP)和歐盟指令。
集成通用電氣的專有LEAPmbr技術(shù),污水廠將是世界上最大的設(shè)備實(shí)現(xiàn)膜生物反應(yīng)器(MBR)技術(shù)項(xiàng)目時(shí)意識到2018年。建筑工程在SKr5.94bn(689.5美元)將在2016年開始。
Henriksdal污水廠歷史和前擴(kuò)張
Henriksdal污水廠成立于1941年,最初的治療能力150000 m³一天,這一天在1953年增加到300000 m³。化學(xué)和生物處理設(shè)施后來被納入工廠的系統(tǒng)。
“污水廠將世界上最大的設(shè)備實(shí)現(xiàn)膜生物反應(yīng)器(MBR)技術(shù)項(xiàng)目時(shí)意識到2018年。”
從1992年4月到1997年4月,主要執(zhí)行擴(kuò)張使植物氮排放量減少約50%,提高磷治療。
另一個(gè)主要的改造工程進(jìn)行了從2007年到2011年,涉及建設(shè)新大廳的凈化和新接收站油脂和有機(jī)廢物。該項(xiàng)目涉及的爆破開挖80000 m³的巖石,使氣味生產(chǎn)設(shè)施被重建并放置在地下。它推動(dòng)了Henriksdalsberget周圍的3000幢新房子的開發(fā)區(qū)。
設(shè)施Henriksdal污水廠
工廠把廢水利用機(jī)械、化學(xué)、生物和砂過濾處理后,處理過的水倒到波羅的海。核電站產(chǎn)生的沼氣作為燃料用于核電站的熱量生產(chǎn)系統(tǒng)生產(chǎn)的電力和生產(chǎn)生物甲烷燃料汽車,而產(chǎn)生的污泥用作土壤改良劑。
污水廠目前配備八機(jī)械屏幕,兩丸室體積為590 m³,兩個(gè)pre-aeration頻道容量為260 m³,13個(gè)主要沉積坦克總額達(dá)到30000 m³,九個(gè)泵站提升primary-sedimentation生物階段,七個(gè)曝氣坦克總額達(dá)到204000 m³和19000中控室內(nèi),五個(gè)增氧機(jī)壓縮機(jī),和14個(gè)二級沉降與總額達(dá)到58000 m³坦克。
此外,工廠配備了12個(gè)水泵將水從生物階段到60砂過濾器、七與總額達(dá)到39000 m³消化器,熱交換器消化池污泥,5000 m³氣柜,五剩余污泥離心機(jī)的50 m³一個(gè)小時(shí),兩個(gè)污泥槽總額達(dá)到10000 m³,四個(gè)離心機(jī)的30 m³/ h的脫水污泥,兩個(gè)筒倉的800 m³含有脫水污泥、4天然氣發(fā)動(dòng)機(jī),三個(gè)鍋爐和相關(guān)設(shè)施。
大約90%的現(xiàn)場設(shè)施位于地下。表面的設(shè)施包括控制中心大樓,機(jī)械處理設(shè)施,污泥的坦克和上層部分污泥增稠劑,消化器、氣柜、氣體收集和天然氣儲存設(shè)施。工廠的舊通風(fēng)煙囪測量80米高,直徑7米目前鋼筋混凝土。
的細(xì)節(jié)Henriksdal污水廠擴(kuò)建和改造項(xiàng)目
測試MBR技術(shù)的試點(diǎn)項(xiàng)目,考慮負(fù)載等于斯德哥爾摩人口預(yù)計(jì)在2040年,于2014年結(jié)束。通用電氣的LEAPmbr技術(shù)于一體的500年ZeeWeed膜超濾技術(shù)是一種先進(jìn)的分離固體,水和廢水的細(xì)菌和病毒。
飛行員在執(zhí)行測試IVL(瑞典環(huán)境研究院)Hammarby Sjostadsverk研究設(shè)施。積極的測試結(jié)果給進(jìn)一步推動(dòng)當(dāng)前項(xiàng)目。擴(kuò)建和改造將使污水廠廢水處理8.64億升的一天。
除了安裝新膜蒸餾單元Henriksdal網(wǎng)站,該項(xiàng)目將包括15公里的地下隧道的建設(shè),無聊從30米至90米低于地面,把廢水從Bromma Henriksdal。新的預(yù)處理設(shè)施組成一個(gè)新的泵站,新的粗篩選和主要沉積盆地也將在Sickla建造。
的退役Bromma污水廠將開始調(diào)試后修改Henriksdal污水廠。
承包商參與瑞典污水廠
重建的規(guī)劃和設(shè)計(jì)作品的污水廠進(jìn)行了從2007年到2011年最忙。2010年,Mercor安裝防火門和蓋茨在現(xiàn)場。
合同交付電氣解決方案包括電信和自動(dòng)化解決方案當(dāng)前項(xiàng)目被授予房顫組。